Howard Ding, Sales Manager

Request a quote

Casting inspection and leak testing

Dimensional, material, internal and leak checks in our own laboratory, agreed per part before production: characteristic, method, sample size, limit and the record you receive.

Send drawing for DFM review Helium leak testing

Enclosed X-ray inspection cabinet with radiation warning label and viewing window
X-ray inspection cabinet.

What we test in our own lab

Equipment alone does not define acceptance. For every part we agree the characteristic, the method, the sample size, the limit and the record you receive, before production.

EquipmentWhat it verifies
Fully automatic CMMGeometry and critical dimensions against the drawing
Video measuring systemTwo-dimensional features and profiles
Calipers and hand gaugesShop-floor dimensional checks
Optical emission spectrometerComposition of the melt and of incoming ingot
Tensile testing machineMechanical properties on test specimens
Hardness testerHardness after heat treatment
X-ray inspectionPorosity and shrinkage in agreed regions
Helium leak detection (sniffer)Leak-tightness below the visible-bubble threshold
Water immersion tankLeak location under internal air pressure
Fully automatic coordinate measuring machine inspecting an aluminum casting
Automatic CMM
Video measuring system for casting dimension checks
Video measuring system
Hardness tester used after heat treatment
Hardness tester
Tensile testing machine in the inspection lab
Tensile tester
Helium leak detector beside a test bench with a cast part clamped in a fixture, a vacuum pump and a helium cylinder
Helium leak detector and test bench
Optical emission spectrometer with argon cylinder and computer workstation
Optical emission spectrometer

Dimensional, material, internal and leak checks

  • Dimensional

    Critical dimensions on the CMM, 2D features on the video system. Fixtures agreed during tooling so the production datum is the inspection datum. Cast-blank and machined tolerances stated separately.

  • Material

    Ingot checked before melting; the melt verified by spectrometer so the pour is confirmed, not assumed. Tensile specimens and hardness after T6 where the drawing requires them.

  • Internal soundness

    X-ray of the regions that matter functionally, with the discontinuity limit and reference standard agreed before the first sample.

  • Leak-tightness

    Helium sniffer and water immersion in-house; pressure testing to an agreed value where a pressure figure is the requirement. Medium, pressure, leak rate and stage stated per part.

Inspection plan by stage

A useful report connects every result to the part: part number and revision, lot or sample, the characteristic, the requirement, the result and the disposition. A material test also states alloy, heat-treatment condition and specimen; a leak test states medium, pressure, units and threshold.

Write a casting inspection plan

StageAgreement to record
Before toolingDrawing revision, critical characteristics, test methods, acceptance limits
First samplesDimensional report scope, material and heat-treatment evidence, functional checks
ProductionSampling or 100% checks by characteristic; lot identification and records
Change or nonconformityContainment, disposition, revalidation and approval responsibilities

Certified quality system

IATF 16949:2016, ISO 9001:2015, ISO 14001:2015 and ISO 45001:2018, held by Qingdao Dechengxin Metal Products Co., Ltd., the production company behind the CEX Casting brand. Numbers, scope and validity are published with the scans.

Certifications, scope and validity

Supplier qualification package

  • Current certificates with site and scope
  • An example inspection report for a comparable part
  • The proposed control plan for your project
  • A factory visit or live video audit of the inspection area

Inspection and leak testing guides

Questions engineers ask

What inspection equipment do you have?
A fully automatic CMM, video measuring system, calipers and gauges, optical emission spectrometer, tensile testing machine, hardness tester, X-ray, helium leak detection and a water immersion tank.
What does an inspection report include?
Part number and revision, lot or sample, each characteristic with its requirement, result and disposition. Material tests state alloy, temper and specimen; leak tests state medium, pressure, units and threshold.
Do you leak test 100% of parts?
Leak testing can be 100% or sampled; it is agreed per part in the inspection plan, together with the stage at which the test is done.
Can I audit the inspection lab?
Yes. Overseas customers can visit the factory or book a live video audit of the inspection area, including records for a comparable part.

Send the drawing and your acceptance criteria

Include the critical characteristics, the leak and X-ray requirements and the reports you need. Howard Ding replies with a proposed inspection plan.

Send a drawing for DFM review

What happens next

  1. Howard Ding confirms receipt and asks for anything missing from the package.
  2. Engineering reviews geometry, alloy and acceptance criteria and proposes a route: squeeze casting, die casting, or a reason neither fits.
  3. You receive the quotation with tooling, samples and validation listed separately from the part price.